Solutions

345/115/23 kV Substation Rebuild

345/115/23 kV Substation Rebuild

Northeast Utility

Commonwealth provided engineering design, material bid packages, and construction bid packages for rebuilding a bulk power substation. The substation consisted of a new 345 kV switchyard for a tapped line, autotransformer, 115 kV breaker-and-a-half switchyard for five lines, 115 kV capacitor bank, two 115/23 kV transformers, two 23 kV switchgear housings, new control house, ac and dc auxiliary systems, protection/relay/control systems, SCADA, and a DFR.

One of the more interesting challenges at the substation was determining the best way to minimize outages as the new substation was constructed near the old one. The basic plan required continued operation of the 34.5 kV distribution system during the construction period. To accomplish this, phased construction and cutover activities were developed to support operational needs.

First, a portion of the new 115 kV and 34.5 kV station was constructed and then interconnected with the existing 115 kV. The interconnection also required some temporary protection circuitry to ensure reliability of the system. Interconnecting the two stations allowed swing of three 115 kV lines from the old station to the new. Also during this period, staged cutovers of 34.5 kV cable circuits occurred.

Second, after reconfiguring the 34.5 kV and 115 kV circuits, it was possible to remove the old 115 kV and 34.5 kV facilities, making room for the new. Existing foundations, duct banks, grounding conduits, equipment, and control house were all removed in this phase.

Third, within the area now cleared, the 115 kV station was finished, the new autotransformer bank installed, and the 345 kV yard constructed. The 345 kV yard was strategically developed to allow tapping of an existing overhead 345 kV line, including consideration for further expansion into a 4-breaker ring bus with a second autotransformer bank.

This solution was implemented in the following market(s):

We are committed, both as a firm, and as individuals to influencing and shaping the secure energy future.

Gary Bernstein, P.E.
Vice President & Chief Marketing Officer

Contact us