138 kV Transmission Line Re-Route Project
Project Date: January, 2024
Type of Client: Utility
Project Region: Midwest
Services Provided: Engineering design, constructability, permitting, easement acquisition, SWPPP development, access studies
The 138 kV Transmission Line Re-Route Project was initiated to support a significant development in the US Midwest. This project required a comprehensive approach to re-routing an existing transmission line to accommodate the new infrastructure.
Project Overview
The utility company embarked on this re-route project to facilitate the construction of a major development. Commonwealth was engaged as the Engineer of Record, providing a range of services including engineering design, constructability and access studies, and the acquisition of necessary state and city permits. Additionally, our Land Services Team conducted a Market Study to assess local land values and secured all required easements along the proposed right-of-way.
Problem
The primary challenge of this project was the acquisition of permits, which involved navigating complex regulatory requirements. The project impacted a flood control dike and a city-owned bicycle and walking path along a river, necessitating approvals from multiple agencies.
Concerns and Issues
- Floodplain Permitting: The project required floodplain permits due to its proximity to a flood control dike.
- DNR Permitting: Approval from the state Department of Natural Resources was necessary due to environmental considerations.
- City Parks Department: The re-route impacted a city-owned bicycle and walking path, requiring coordination with the city parks department.
Solution
To address these challenges, Commonwealth provided a detailed constructability and access study, ensuring that all potential issues were identified and mitigated. Our team successfully navigated the permitting process, securing the necessary approvals from the floodplain authorities, DNR, and the city parks department.
The Land Services Team's Market Study and easement acquisition efforts ensured that all land-related concerns were addressed, allowing the project to proceed smoothly. By leveraging our expertise in engineering design and regulatory compliance, Commonwealth facilitated the successful re-routing of the 138 kV transmission line, supporting the development of central Indiana's infrastructure.
Commonwealth Associates is your reliable partner for transmission line re-routes. Our team excels in engineering design, constructability assessments, and regulatory compliance, ensuring smooth project execution. With expertise in permitting, easement acquisition, and environmental impact studies, we handle challenges efficiently. Choose Commonwealth for innovative solutions tailored to your needs. Contact us today!